Cepsa entrusts Aitesa to carry out the efficiency improvement of YB-3 waste heat recovery boiler in Cepsa-Refinery “Gibraltar-San Roque”.
The project consists of:
– Adapting of the waste heat recovery boiler to utilize fuel gas in place of a conventional fuel such as fuel oil and NOx reduction by changing the model of burner to Low NOx burner;
– Design, manufacture and installation of a new economizer;
– Complete overhaul of waste heat recovery boiler;
– New casing, refractory and insulation of the boiler;
– Adapting of the installation to the control loop and safety;
– Design and supply of new lighting control panel and monitoring of burners;
– Lighting.
The execution time of the project is 10 months.